Tesco Extra
Lincoln

We were approached by Faithfull & Gould initially to look at a scheme for their new Tesco Extra store in Lincoln. The scheme required a very quick site installation to fit in with the client’s main-store building programme.

The scheme was split into two parts, the first was to design and deliver 5 retail shops which in parts had an internal soffit height of nearly 6m and the second was to provide 2 elliptical retail shops which would be the first of their kind. The retail units had to be designed to be in keeping with the new store. The 6m soffit height was delivered by installing a top hat extension to the modules and the entrances had a curtain wall frontage which was installed onsite.

Tesco leased the 3 central retail units to a national gym chain. Due to the future proofing of Eco Modular Buildings system we were able to accommodate the new requirements of Tesco and the gym with ease. We removed the party walls and the floor covering and re-laid the floor using a Cement Particle Board thus meeting the 7kn loading and the reverberation levels that the gym required. These additional works were completed in 5 days and didn’t affect the already tight programme.

Eco Modular Buildings Designed, Manufactured and installed the building to the tight 16 week programme. We are currently working with Tesco to deliver a pilot scheme for an existing store to provide additional retail units.

Building size
740sqm

Building Size

Manufacturing period
8 weeks

Manufacture

Installation time
7 weeks

Installation